What's New at SRM
Latest Post
Celebrating Success at Lumen Field
We are incredibly honored to have been recognized by the Puget Sound Business Journal as one of Washington’s 100 Fastest-Growing Private Companies, coming in at #3. Thank you, PSBJ, for
More News
Merrill Gardens at Ballard goes Vertical
The crew at Ballard has been working hard to get the mass excavation complete. Structural excavation is finished and the lower level slab-on-grade is scheduled to be in place by
Google Phase II – Progress continues
Google Phase II is progressing well with several recent completions to report including permanent power! The roof top cap is complete on Zone 1 and the southern half of Zone
SRM News – January 2015
Construction on Merrill Gardens at Lafayette wrapped up in October 2014 and the building is being well received by residents. SRM Development currently has six projects underway. For all the
Bellevue & Main Progress
Bellevue at Main is nearly topped out! We are currently framing the fourth and fifth levels and wood framing will continue over the next several weeks. Electrical and plumbing systems
The Astro – Taking Shape
The scaffolding on Harrison and the north half of 1st Avenue N has been taken down revealing the exterior. The interiors are coming together and the units are scheduled to
“SRM Development Jumps Into Oakland Multi-Family Housing”
To view the article, “SRM Development jumps into Oakland multi-family housing with Temescal apartments,” please click here.
The Astro – On Schedule for Spring of 2015
At the Astro project crews are working on wrapping up unit finishes and the exterior envelope. Drywall crews are hanging the last residential floor and will begin the main level
Google Phase II – Crews Working at Full Stride
We are making great progress on Phase II of the Google project and are scheduled to turnover the shell and core in April 2015. The last elevated structural concrete slab
Bellevue Way at Main Goes Vertical!
Bellevue Way at Main is going vertical! We poured half of the podium level concrete deck last month and have begun wood framing on the first of four floors. We
The Astro – On Target
The Astro is on target to be completed by the end of March 2015. Cabinets and wood flooring have been installed on the 6th floor. Roof planting in on schedule
Google Phase II Progress
Google Phase II is currently 20% completed with the mass excavation and 95% completed with the hydro carbon clean up. There still remains some VOC clean up in the North
Merrill Gardens at Huntington Beach – A Complete Success
SRM Development has recently completed another signature Merrill Gardens project in Huntington Beach California. This Merrill Gardens is a cottage style facility with exterior stone and lap siding elements reminiscent
The Astro Apartments – A Winning Combination of Design & Development
SRM Development, LLC was recently recognized for another outstanding job in design & development. Judges for the 2014 Gold Nugget Awards have given The Astro Apartments located in Seattle, WA
101 Taylor – Building of the Century
The Century project is in the process of wrapping up all interior finishes and preparing for final inspections. Curb, gutter, and sidewalk improvements are being installed at the street level
Lafayette – Exterior Wrapping Up, Interior Underway
With the exterior structure reaching completion, additional exterior work is in motion. Sidewalks and stairs were poured on the south side & the courtyard fountain was installed. In the meantime,
The Astro – Progressing Into Summer
The Astro continues to make rapid progress as we go into the summer. On the lower parking garage levels, the garage lighting is installed and the utilities on the lower
Structural Excavation Complete at Google Phase II
May has been a big month at Google Phase II. Structural excavation has reached completion, while 10 out of 12 SOG’s have been poured. The 11th and 12th SOG’s are
Bellevue Way Ventures Update
Concrete crews have completed 35,000 SF of slab on grade this month and have the shoring and decking for the first of three elevated slabs in place. Footing and shear
Google Phase II – Moving Right Along
Through the month of April, crews poured 96 columns and column footings. There are 22 footings and columns left to go before we start forming the north wall. Five out
Lafayette – Exterior Wrapping Up
Workers are wrapping up the exterior cladding and site work is scheduled to be complete at the end of May. Mechanical, electrical, and plumbing rough in is wrapping up and
Huntington Beach – Nearing Occupancy
Huntington Beach is nearing occupancy. Workers are diligently putting final touches on the building and site work. Final inspections are in progress and residents are scheduled to move in by
101 Taylor Completes Residential Drywall
Crews are now complete with all residential drywall work. Common area drywall will continue through May. Exterior cladding at the roof level is wrapping up and we are working on
The Astro Moves Forward
The Astro continues to move along at a good pace and the team is working hard to keep the momentum going. On the ground level there are a few ‘feature’
Bellevue Development
Workers are currently forming and pouring structural footings, walls, and columns at the SW and SE quadrants in advance of our first SOG pour on 4/16. The first shortcrete perimeter
101 Taylor Completes Units
This month we will be installing gypsum wall board in the last of the L9 and ground floor Townhouse units. Finish paint is complete on levels three and four, and
Lafayette Progress
The exterior envelope work is wrapping up and site work is in progress. Storefront glazing systems will be complete by the end of April. The interior mechanical, electrical, and plumbing
2013 Award of Merit – Best Multi-Family Housing Project
2013 PCBC Presents Award of Merit Honors to SRM Development, LLC for the Lyric in Seattle for the Best Multi-Family Housing Project – Over 60 Du/Acre.
2013 Built Green Hammer Award
SRM Development, LLC received the 2013 Built Green Hammer Award in the Builder, Multi-Family 150+ Units category for the Lyric Project. The Built Green Hammer Awards recognize Built Green members
Bellevue at Main Commences Site Demolition
The Bellevue at Main Project got underway last week. Underground utilities on Main Street will be completed this coming weekend. Site demolition is underway and the installation of soldier piles