Bellevue Way Ventures Update

Concrete crews have completed 35,000 SF of slab on grade this month and have the shoring and decking for the first of three elevated slabs in place. Footing and shear walls continue to advance and our next slab on grade pour will be on May 6th. The garage slab, ramp on grade, and first two post-tensioned concrete slabs will be completed by the end of May.

Scroll to Top
Scroll to Top