May has been a big month at Google Phase II. Structural excavation has reached completion, while 10 out of 12 SOG’s have been poured. The 11th and 12th SOG’s are scheduled to be poured in June.
8 PT decks were poured this month. As a result of the large floor plate, we are going vertical on the south end of the site as we continue to pour with intermediate tensioning. Over the past few weeks all ground level columns, footings, cores and shear walls have been poured. Work continues on the underground drainage, plumbing and electrical on the north end of the site.