Google Phase II Progress
Google Phase II is currently 20% completed with the mass excavation and 95% completed with the hydro carbon clean up. There still remains some VOC clean up in the North …
Google Phase II is currently 20% completed with the mass excavation and 95% completed with the hydro carbon clean up. There still remains some VOC clean up in the North …
SRM Development has recently completed another signature Merrill Gardens project in Huntington Beach California. This Merrill Gardens is a cottage style facility with exterior stone and lap siding elements reminiscent …
Merrill Gardens at Huntington Beach – A Complete Success Read More »
The Century project is in the process of wrapping up all interior finishes and preparing for final inspections. Curb, gutter, and sidewalk improvements are being installed at the street level …
With the exterior structure reaching completion, additional exterior work is in motion. Sidewalks and stairs were poured on the south side & the courtyard fountain was installed. In the meantime, …
Lafayette – Exterior Wrapping Up, Interior Underway Read More »
The Astro continues to make rapid progress as we go into the summer. On the lower parking garage levels, the garage lighting is installed and the utilities on the lower …
May has been a big month at Google Phase II. Structural excavation has reached completion, while 10 out of 12 SOG’s have been poured. The 11th and 12th SOG’s are …
Structural Excavation Complete at Google Phase II Read More »
Concrete crews have completed 35,000 SF of slab on grade this month and have the shoring and decking for the first of three elevated slabs in place. Footing and shear …
Through the month of April, crews poured 96 columns and column footings. There are 22 footings and columns left to go before we start forming the north wall. Five out …
Workers are wrapping up the exterior cladding and site work is scheduled to be complete at the end of May. Mechanical, electrical, and plumbing rough in is wrapping up and …