Construction Update

Gridline Apartments

September 2022

About the Project

The Gridline Apartments will consist of two buildings — a north and west building. The North Building will be 161,601 s.f. with 2,850 s.f. of common amenity space and 129 units. Community amenities will include a fitness room, rooftop club room, and a roof deck with incredible skyline views, vegetated roof areas, custom BBQ table, and outdoor fire tables. The North Building also offers multiple bike storage rooms, a secured parcel room, a tranquil courtyard, and roughly 1,256 s.f. of co-working space to accommodate the teleworking lifestyles. The West Building (31,261 s.f., 49 units) will include  two secured bike storage rooms, secured parcel room, and a roof deck with sweeping view, BBQ, fire table and vegetated roof areas.

Scheduled completion date is Q4 2023

Scheduled Work:

We are almost out of the excavated site and approaching street level at the North Building! Concrete levels are expected to finish by mid-October and then wood framing will commence.

Over at the West Building, the slab on grade was poured last week and we will soon see vertical progress as work begins on the first PT slab! Wood framing is scheduled to start by the first week of October.

Noise Variance Notification

On Tuesday, September 27th, we will be pouring the North portion of L1 level concrete PT slab at the NORTH BUILDING (1421 Harvard Ave). Please be aware there will be some additional noise between 6am and 7am. Please click here to view permit.

Planned Street Interruptions

Vehicular and pedestrian traffic on Harvard Avenue will remain slow as we continue to facilitate safety during construction and staging activities for construction vehicles/hauling trucks. Neighbors are requested to follow the temporary “NO PARKING” signs on E. Union and both ends of Boylston between E. Union and E. Pike.

We apologize for any inconveniences throughout the construction process. The safety of all employees, neighbors and the general public is our number one priority. Please be aware of changing conditions in the public right-of-way as sidewalk and street conditions are ever changing. Heavy equipment is entering and exiting the jobsite regularly. Please be aware of your surroundings and help us keep this project safe and free of injury.

Thank you.

Hours of Operation

7:00am – 6:00pm, Monday through Friday & non-legal holidays

9:00am – 6:00pm, Saturdays and legal holidays

No work on Sundays unless it’s an emergency.

Work outside of permitted hours (such as specified holidays) may occur on a case by case basis as approved by Building Services Department.

Stay Notified About This Project!

    Contact Us

    Danielle Locklar

    Senior

    Project Manager

    831.277.8680

    Bill Robinson

    Project Manager

    714.794.7710

    Christian Dobbins

    Project Engineer

    503.310.6447

    Jyoti Bhadrashetti

    Project Engineer

    415.712.9789

    James Wilkins

    Project

    Superintendent

    425.772.0107

    Scroll to Top