Workers are currently forming and pouring structural footings, walls, and columns at the SW and SE quadrants in advance of our first SOG pour on 4/16. The first shortcrete perimeter wall was completed 3/24 and we will be shooting walls the balance of this week. Footing excavation is continuing in the NW and NE quadrants. Underground plumbing structures at the garage level will be installed next week.