This month we will be installing gypsum wall board in the last of the L9 and ground floor Townhouse units. Finish paint is complete on levels three and four, and crews are cleaning and locking finished units behind the painting crews. The exterior metal panels are substantially complete and that work will wrap up in April. The tower crane and most of our exterior scaffolidng has been dismantled and elevator crews will start the second elevator core this month.