The crew at Ballard has been working hard to get the mass excavation complete. Structural excavation is finished and the lower level slab-on-grade is scheduled to be in place by the end of April. We anticipate structural concrete to wrap up in July. The 140 foot tall tower crane is operational and has a 180 foot reach that can hoist 8,000 pounds at the tip!